Barakah Nuclear Power Plant - 2015

  • Barakah Nuclear Power Plant - 2015

  • Client : ENEC
  • Main Contractor : ISCO
  • Size : 914mm, SDR17
  • Quantity : 6,480 m
  • Material : HDPE
  • Scope : Supply & Welding of Safety Related HDPE Pipes & Fittings

Borouge Two Expansion (B2) Project - 2007

  • Borouge Two Expansion (B2) Project - 2007

  • Client : Borouge
  • Main Contractor : Tecnicas Reunidas
  • Size : 1,600mm, SDR 26
  • Quantity : 26,000 m
  • Material : HDPE
  • Scope : Seawater Supply & Return - Supply, Welding, Installation & Testing

Polypropylene Fifth Unit (PP-5) - 2020

  • Polypropylene Fifth Unit (PP-5) - 2020

  • Client : Borouge
  • Main Contractor : Tecnimont
  • Size : 1,600mm, SDR 11
  • Quantity : 11,172 m
  • Material : HDPE
  • Scope : Cooling Water Supply & Return and Potable & Fire Water

Effluent Oily Water Supply to Oil Production Platform - 2013

  • Effluent Oily Water Supply to Oil Production Platform - 2013

  • Client : ZADCO
  • Main Contractor : APS
  • Size : 560mm, SDR 7.25
  • Quantity : 6,400 m
  • Material : HDPE
  • Scope : EPC Contract

15 MIGD SWRO Desalination Plant - 2014

  • 15 MIGD SWRO Desalination Plant - 2014

  • Client : (FEWA) - Ras Al Khaimah
  • Main Contractor : Actco
  • Size : 1,800mm, SDR17
  • Quantity : 1,600 m
  • Material : HDPE
  • Scope : Supply, Installation & Testing

Hydroelectric project - 2020

  • Hydroelectric project - 2020

  • Client : Alaska Energy Authority , USA
  • Main Contractor : Orion
  • Size : 1,600mm, SDR 21
  • Quantity : 2,500 m
  • Material : HDPE
  • Scope : Supply

Al Hair Sewage Treatment Plant (STP)

  • Al Hair Sewage Treatment Plant (STP)

  • Client : National Water Co. - Riyadh, KSA
  • Main Contractor : Saudi Tumpane Company
  • Size : 3,000mm x 100mm thickness
  • Quantity : 1,324 m
  • Material : HDPE
  • Scope : Supply

Supply of Slurry Water HDPE Pipelines for New Phosphate Plant (Wa’ad Al Shamal) - 2016

  • Supply of Slurry Water HDPE Pipelines for New Phosphate Plant (Wa’ad Al Shamal) - 2016

  • Client : MAADEN MINES - KSA
  • Main Contractor : Kepco
  • Size : 710mm-1200mm, SDR 11 and 1400mm-1600mm, SDR 26
  • Quantity : Total 15,400 m
  • Material : HDPE
  • Scope : Supply

1320 MW Thermal Power Plant SWIO – Gayathri Power - 2013

  • 1320 MW Thermal Power Plant SWIO – Gayathri Power - 2013

  • Client : NCC Power Projects - Krishnapatnam, Nellore Dist., Andhra Pradesh, India
  • Main Contractor : Gayatri Lt.
  • Size : 1,400mm & 1600 mm, SDR 26
  • Quantity : 3,100 m
  • Material : HDPE
  • Scope : Supply

55MW Methane Gas Power Project

  • 55MW Methane Gas Power Project

  • Client : Shema Power Lake Kivu Ltd. (SPLK) - Rwanda
  • Main Contractor : ISCO
  • Size : 315mm, 400mm, 800mm, 1,200mm and 1,400 mm
  • Quantity : Total 32,970 m
  • Material : HDPE
  • Scope : Supply

Sea Water Intake for RRE Project

  • Sea Water Intake for RRE Project

  • Client : Takreer
  • Main Contractor : Samsung
  • Size : 3,000mm
  • Quantity : 16,400 metres (Offshore)
  • Material : Polypropylene Pipe (PP)
  • Scope : EPC Contract

Sea Water Outfall for RRE Project

  • Sea Water Outfall for RRE Project

  • Client : Takreer
  • Main Contractor : Samsung
  • Size : 2,000mm
  • Quantity : 22,500 metres (Onshore)
  • Material : Polypropylene Pipe (PP)
  • Scope : EPC Contract

Underground HDPE Onshore for Borouge 3 Project (U&O)

  • Underground HDPE Onshore for Borouge 3 Project (U&O)

  • Client : BOROUGE
  • Main Contractor : Hyundai
  • Size : 2,000mm to 63mm PN20 to PN6.3
  • Quantity : 110,000 Metres
  • Material : HDPE
  • Scope : Supply & Installation

Underground HDPE Onshore for Borouge 3 Project (LDPE & PO Plant)

  • Underground HDPE Onshore for Borouge 3 Project (LDPE & PO Plant)

  • Client : BOROUGE
  • Main Contractor : Contractor : TSJ
  • Size : 2,000mm to 63mm PN20 to PN6.3
  • Quantity : 18,000 Metres
  • Material : HDPE
  • Scope : Supply & Installation

Effluent Water Injection Line

  • Effluent Water Injection Line

  • Client : ZADCO
  • Operating Pressure : 25 bar
  • Size : 560mm SDR7.27
  • Quantity : 4,600 Metres (Offshore)
  • Material : HDPE
  • Scope : EPC Contract

Polypropylene (PP) Water Tank

  • Polypropylene (PP) Water Tank

  • Location : Al Rawdha in Al Ain , UAE
  • Capacity : 1.5 million litres
  • Material : Polypropylene Pipe (PP)
  • Scope : Supply & Installation

Irrigation Mains in Abu Dhabi Industrial City

  • Irrigation Mains in Abu Dhabi Industrial City

  • Client : ADSSC
  • Project : Irrigation Mains to 450mm diameter PN16
  • Material : HDPE
  • Total Length : 85kms
  • Scope : Supply of pipes, welders, welding machinery

Sewage Rising Mains in Mafraq

  • Sewage Rising Mains in Mafraq

  • Client : ADSSC
  • Project : Sewage Rising Mains 630mm diameter PN16
  • Material : HDPE
  • Total Length : 72kms
  • Scope : Supply of pipes, welders, welding machinery

Sewage Effluent Mains in Al Ain

  • Sewage Effluent Mains in Al Ain

  • Client : ADSSC
  • Project : Sewage Effluent Mains 1200mm diameter PN10
  • Material : HDPE
  • Total Length : 22kms
  • Scope : Supply of pipes, welders, welding machinery

Irrigation Mains in Abu Dhabi

  • Irrigation Mains in Abu Dhabi

  • Client : ADSSC
  • Project : Irrigation Mains 900mm diameter PN10
  • Material : HDPE
  • Total Length : 9kms
  • Scope : Supply of pipes, welders, welding machinery

Occidental Petroleum, Qatar

  • Occidental Petroleum, Qatar

  • Client : APS
  • Project : Effluent Water Line 630mm diameter PN22
  • Material : HDPE
  • Total Length : 6kms
  • Scope : Supply of pipes and fittings

Abu Dhabi Corniche Development

  • Abu Dhabi Corniche Development

  • Client : Abu Dhabi Municipality
  • Project : Corniche Development, Surface Water Drainage up to 1200mm diameter PN10
  • Material : HDPE
  • Total Length : 10kms
  • Scope : Supply of pipes, welders, welding machinery